DISMISSED
Court
High Court of Uttarakhand
Decided
7 November 2024
Bench
Manoj Kumar Tiwari, Vivek Bharti Sharma
Case no.
WPMB 520/2024

Follow Uttarakhand High CourtFollow Manoj Kumar TiwariFollow Vivek Bharti Sharma

Judgment

SL. No. Dat e Office Not es, r epor t s, or der s or pr oceedin gs or dir ect ion s an d Regist r ar 's or der w it h Sign at u r es COURT'S OR JUDGE'S ORDERS

WPMB No.520 of 2024 Hon 'ble Man oj Ku m ar Tiw ar i, A.C.J. Hon 'ble Viv ek Bh ar t i Sh ar m a, J.

Mr. Mani Kumar, Advocate for the petitioner.

Mr. S.S. Lingwal, Advocate for the respondents.

¶2Petitioner is a Civil Contractor registered with G.B. Pant University of Agriculture & Technology, Pant Nagar.

¶3By means of this writ petition, petitioner has sought following reliefs:

"(A)issue a writ, order or direction in the nature of certiorari with a prayer to quash the order dated

08.10.2024 (Annexure No-6) passed by the office of Vice chancellor Govind Ballabh Pant University Agriculture and Technology Pantnagar, Udham Singh Nagar where by E-Tender dated 15.02.2024 published by the office of Respondent No-2 as per e-Procurem ent System, Government of Uttarakhand for the construction of Boundary wall, Gate and Approach Road of SC ST Hostel

(Male) was cancelled.

(B) issue a writ, order or direction in the nature of writ of Mandamus directing the respondent no. I to award the contract in pursuance of E-Tender dated 15.02.2024 published by the office of Respondent No-2 for the construction of Boundary wall, Gate and Approach Road of SC.ST Hostel (Male)."

¶4Petitioner is aggrieved by an order passed by Vice Chancellor of aforesaid University, on 08.10.2024. By the said order, Vice Chancellor had called explanation from concerned authorities, as to why tender notice was not published in the newspapers. Vice Chancellor further directed to issue show cause notice to all persons responsible for this lapse. Vice Chancellor also

directed the authorities to float fresh tender notice immediately. Pursuant to orders passed by Vice Chancellor, the tender process initiated vide tender notice dated

15.02.2024 has been cancelled.

¶5Petitioner submits that since he was one of the bidders, who participated in the earlier tender process initiated vide notice dated 15.02.2024 and his bid was found to be the lowest and his name was also recommended by Building Committee to the Vice Chancellor for approval, therefore, earlier tender notice could not have been cancelled and thus, he has sought a mandamus to award the contract to him in view of lowest rates offered by him in his bid.

¶6Learned counsel for the University, however, submits that petitioner does not have any legally enforceable right and merely because he was found to be the lowest bidder, cannot be a ground to award contract to him.

¶7We find substance in the said submission. The bid submitted by the petitioner is in the nature of offer and until his offer is accepted by employer, it does not give him reason to question the validity of the decision taken by the Vice Chancellor. There is nothing on record to show that petitioner's bid was accepted. Reliance on the letter of Building Committee is of no avail to the petitioner, as by the said letter, only recommendation was made in favour of the petitioner, which was not accepted.

¶8Even otherwise also, decision to cancel the tender process is referable to

one of the clause of the tender process, which provides that Tender Committee can reject one or all the bids received for the tender process.

¶9Learned counsel for the petitioner submitted that the sole ground for cancelling the tender process appears to be that the tender notice was not published in the newspapers. He submits that E-tender was invited and, in case of E-tender, there is no requirement of publication of tender notice in newspapers and this aspect has been admitted by the Deputy Director in his letter.

¶10Be that as it may, since the Vice Chancellor has found fault with the manner, in which the tender process was initiated and has also called explanation from concerned authorities, therefore, we do not find any reason to go into the question of validity of the decision taken by the Vice Chancellor. Thus, there is no scope for interference.

¶11Accordingly, the writ petition fails and is dismissed.

( Viv ek Bh ar t i Sh ar m a, J.) ( Man oj Ku m ar Tiw ar i, A.C.J.)

07.11.2024 Arpan

ARPAN JAISWAL DN: c=IN, o=HIGH COURT OF UTTARAKHAND, ou=HIGH COURT OF UTTARAKHAND,

2.5.4.20=eabb68a3895e41937c266c23964c0485365445e3a20d ddb7393398f9fe45ba3e, postalCode=263001, st=UTTARAKHAND, serialNumber=060FC17022BEAE3DE215D68D9D454C5109CB98 7446351E4DF04AADAA2C2CEA66, cn=ARPAN JAISWAL Date: 2024.11.08 14:20:24 +05'30'

Source: High Court of Uttarakhand, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.