- Court
- High Court of Uttarakhand
- Decided
- 28 December 2023
- Bench
- Rakesh Thapliyal
- Case no.
- WPMS 1596/2023
Follow Uttarakhand High CourtFollow Rakesh Thapliyal
Judgment
Sl. No Date Office Notes, reports, orders or proceedings or directions and Registrar's order with Signatures COURT'S OR JUDGES'S ORDERS
WPMS No.1596 of 2023 Hon'ble Rakesh Thapliyal, J.
¶1Mr. Amar Murti Shukla, learned counsel, along with Mr. Anand Singh, learned counsel for the petitioner.
¶2Mr. Jagdeesh Singh Bisht, learned Standing Counsel for State of Uttarakhand.
¶3Mr. Jitendra Chaudhary, learned counsel for respondent no.3.
¶4By means of the instant petition, the petitioner is praying for the following reliefs:- "a). Issue a writ order or direction in nature of Certiorari quashing notification dated
27.03.2023 (Annexure-3) issued by respondent no.1. b). Issue any other order or direction which this Hon'ble Court may deem fit and proper in the circumstances of the case. c). Award cost of the petition."
¶5The Annexure No.3, which is the impugned notification, is only a proposed modification, wherein, the objections have been invited. This impugned notification further stipulates that the date, time and place will be intimidated separately. This notification was stayed by this Court on
06.06.2023 after taking into consideration the mandate of Section 102 of the Act.
¶6On the day when this proposed notification was stayed, this Court takes into consideration the statement, as given by the State Counsel that the date and place has subsequently been notified by the virtue of an Office Memorandum. The Court was of the view that whether the date place, notified by subsequent other communications, meet the requirements, as given in Section 102 of the Act. Section 102 of the Act is being extracted as hereinbelow:-"102. Cancellation or modification of scheme.-(1) The State Government may, at any time, if it considers necessary, in the public interest so to do, modify any approved scheme after giving-
(i) the State transport undertaking;
(ii) any other person who, in the opinion of the State Government, is likely to be affected by the proposed modification.
an opportunity of being heard in respect of proposed modifications.
(2) The State Government shall publish any modification proposed under sub-section (1) in the Official Gazette in one of newspapers in regional languages circulating in the area in which it is proposed to be covered by such modification, together with the date, not being less than thirty days from such publication in the Official Gazette, and the time and place at which any representation received in this behalf will be heard by the State Government."
¶7Sub Section 2 of Section 102 of the Act clearly provides that State Government shall publish any modification proposed under sub-section
(1) in the Official Gazette and in one of the newspapers in the regional languages circulating in the area in which it is proposed to be covered by such modification, together with the date, not being less than thirty days from such publication in the Official Gazette, and time place at which any representation received in this behalf will be heard by the State Government.
¶8The mandate of Sub-Section 2 of Section 102 of the Act is very clear, which is evident from the impugned notification, which clearly provides that any person may file objections within 30 days from the date of publication of the proposed notification in the Gazette.
¶9Clause of notification further provides that the date, time place will be intimated subsequently to the petitioner.
¶10As it appears from the proposed modification that the objections were invited and the time is also stipulated therein that objections may be submitted within 30 days from the date of its publication and that condition is clearly mentioned in notification.
¶11So far as the date, time and place for hearing the objections are concerned, in this impugned notification, it is clearly mentioned that it will be communicated later on, and once it is mentioned that the date, time place will be communicated later on is sufficient to fulfill the mandate of Section 102 (2) of the Motor Vehicle Act.
¶12If we further scrutinize Section 102(2) of the Act, the mandate of this provision is that before finalizing the scheme, objections should be considered, in proposed notification, it is clearly mentioned that objections will be furnished within 30 days, and so far as the date, time and place is concerned, this is only for deciding the objections.
¶13Merely because the date, time and place is not mentioned in the proposed notification, it does not mean that the mandate of Section 102 of the Act has not been fulfilled. In notification, there is reference of date, time and place with this stipulation that the same will be notified later. Therefore, this Court is of the view that the notification meets all requirements of Section 102 of the Act.
¶14Apart from this, by issuing this proposed notification, the petitioner is not prejudice at all. He still has a right to file objections simultaneously, respondent-authorities are also under legal obligation to decide those objections. In view of this, the petition is thoroughly misconceived and is a premature petition, and only because of technical objection, this petition has been filed by the petitioner, who is a private existing operator and the notification was stayed by this Court on 06.06.2023. Therefore, this Court is of the view that this petition deserves to be dismissed with exemplary cost of Rs. 1 Lakh on the petitioner.
¶15Learned counsel for the petitioner lastly submits that the cost may not be imposed.
¶16On his request, the order imposing the cost is recalled.
¶17Thus, the petition, being devoid of merit, is dismissed. No order as to cost.
(Rakesh Thapliyal, J.)
28.12.2023 Reena
Source: High Court of Uttarakhand, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.