ORDER The present Civil Miscellaneous Petition has been filed to condone the delay of 543 days in preferring the Revision Petition.
¶2Heard the Petitioner-in-Person and the learned counsel for the respondents.
¶3The Petitioner-in-Person states that he had filed Writ Petition before this Court. The Hon'ble First Bench of this Court in W.P.No.2654 of 2024 by an order dated 07.02.2024 disposed of the writ petition giving liberty to the Petitioner-in-Person to avail remedy under law, challenging the judgment and decree before the Principal District Munsif, Villupuram dated
29.08.2022 in S.C.No.2 of 2019.
¶4The Petitioner-in-person therefore states that revision is maintainable and in view of his agitating the matter in the Writ jurisdiction, the delay had occasioned. He therefore seeks for condonation of delay in 543 days.
¶5Per contra, the learned counsel for the respondents would state that remedy available to the Petitioner-in-Person is by approaching DRAT and not by way of Article 227, by a revision before this Court. He would also state that only in order to avoid the mandatory pre-deposit to be made under the provisions of the DRAT Act, the present revision petition has been filed. Any how, presently I am concerned only with an application to condone the delay in filing the revision. The Principal District Munsif Court, Villupuram, in and by a judgment and decree dated 29.08.2022 has dismissed the suit. An appeal remedy is available even under the provisions of the CPC to the competent Sub Court.
¶6Therefore, there is no purpose in entertaining the present revision when a statutory appeal remedy is available to the Petitioner-in-Person. If at all such an appeal is preferred, the same shall be dealt with in accordance with law and shall be open to the respondents / banks to contend that the suit is not maintainable and the remedy open on the petitioner is only to prefer an appeal before the DRAT.
¶7The learned counsel for the respondents also states that delay is 543 days only if the order under challenged is the order of the DRAT and if the order of the Principal District Munsif Court, Villupuram is under challenge, then the delay would be much more. However, in view of the fact that, I am dismissing the condone delay application, giving liberty to the Petitioner-in-Person to file a regular First Appeal before the Sub Court, this contention of the learned counsel for the respondent does not assume much significance, in the context of the present matter.
¶8With the above observations, this Civil Miscellaneous Petition is dismissed. 12-09-2025 jas To The Principal District Munsif Court, Villupuram. P.B. BALAJI,J. jas CMP.No.7179 of 2025 in CRP.SR.No.66066 of 2024
12.09.2025
Case details
Parties and counsel
IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 12-09-2025 CORAM THE HONOURABLE MR.JUSTICE P.B. BALAJI CMP.No.7179 of 2025 in CRP.SR.No.66066 of 2024 Dr.K.Rayar .. Petitioner-in-Person Vs 1.The Chairman, Central Office, Indian Overseas Bank, H.O No.763, Anna Salai, Chennai – 600 002. 2.The General Manager, Central Office, Indian Overseas Bank, H.O, No.763, Anna Salai, Chennai – 600 002. 3.The Chief Regional Manager, Indian Overseas Bank, Regional Office, 5 Road Salem – 6. 4.The Branch Manager, Indian Overseas Bank, Villupuram Branch, No.719, Sri Santhinathan House, Nehruji Road, Villupuram District. .. Respondent(s) For Appellant(s): Dr.K.Rayar (P-in-P) For Respondent(s): Mr.I.M.Siddartha Ramarajan for Mrs.V.Rajeshwari
Source: High Court of Madras, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.