VoxJuris
Home › High Courts › Jammu and Kashmir High Court 2025 › High Court of Jammu and Kashmir and Ladakh

Shah Technical Consultants Private Limited v. Union Territory of J and K (Jal Shakti / Phe)

Disposed Off
Court
High Court of Jammu and Kashmir and Ladakh
Decided
5 December 2025
Bench
Sanjeev Kumar, Judge
Case no.
Arb P 48/2024

Follow Jammu and Kashmir High CourtFollow Sanjeev KumarFollow Judge

Judgment

JUDGMENT

05.12.2025

¶1This is a petition filed by Shah Technical Consultants Private Limited under Section 11(6) of the Arbitration & Conciliation Act, 1966, ["the Act"] seeking appointment of an independent Arbitrator.

Page 2

FACTUAL MATRIX:

¶2The UT of J&K, the respondent herein, initiated a UT level Project Development & Management Consultancy ["PDMC"] for Atal Mission for Rejuvenation and Urban Transformation ["AMRUT 2-0"]. The main objective of the project was to provide potable drinking water tap connections to new households, ensure universal household coverage of sewerage and septage services in 500 AMRUT Cities in India, rejuvenation of water bodies & development of green spaces and parks around such water bodies etc., etc.

¶3The petitioner participated in the bidding process and was appointed as the PDMC for AMRUT-2.0 Project launched by the Government of India in UT of Jammu & Kashmir vide Allotment Order No. CE/PHEK/01 of 2023-24/12352-417 dated 12.07.2023 issued by the Chief Engineer, Jal Shakti, Kashmir. The parties also signed an agreement on 13th July, 2023.

¶4The scope of the work included Design, Estimation, Procurement, Supervision and Project Management for AMRUT-2.0 in the Jammu & Kashmir Region. The contract was valued at Rs. 27.18 crores approximately which was to subsist for a period of 34 months. The petitioner, as is claimed, at the time of engagement, had provided a bank guarantee for an amount of Rs. 81.54 lacs as security in terms of the agreement. It is claimed by the petitioner that right from the very beginning, the petitioner faced difficulties in smooth execution of the assigned job. There was delay on the

Page 3

part of Jal Shakti, Department in getting approval of the Project Feasibility Reports from the Government of India. It is submitted that Project Feasibility Reports were received by the petitioner only on 1st August, 2023 for some projects, and for rest these were received in the month of September, 2023.

¶5It is submitted that despite the difficulties created by the respondent, the petitioner was able to deliver 73 Detailed Project Reports complete in all respects, out of which the respondent approved 49 projects. It is further submitted that the petitioner also completed 81 project surveys which were communicated to the respondent for approval. It is alleged that despite making significant progress, the petitioner did not receive payment amount to the tune of Rs. 6.88 crores and, therefore, requested the respondent to clear its dues. It is alleged by the petitioner that the respondent instead of clearing the dues initiated termination of the contract vide communication dated 18th July, 2024 citing delays and quality concerns.

¶6It is submitted by the learned counsel for the petitioner that the termination notice was challenged in Arbitration Petition filed under Section 9 of the Act before the Civil Court, and the Civil Court vide order 24th July, 2024 granted an interim stay restraining the respondent from unilaterally terminating the contract or invoking the banks guarantee pending resolution of disputes through arbitration.

¶7In view of the aforesaid differences, the petitioner claims that he was constrained to serve a notice dated 8th August, 2024 upon the respondent for appointment of an Arbitrator. However, the

Page 4

respondent did not act upon the said notice nor agreed to the appointment of the Arbitrator in terms of Clause 15 of the Contract. Having failed to persuade the respondent to appoint an Arbitrator to resolve the disputes arising out of the contract, the petitioner has filed the instant petition.

¶8The petition has been resisted by the respondent by filing objections. In the objections, the Arbitration Clause i.e. Clause 15 of the Contract agreement has not been disputed. It is also not disputed that the respondent had initiated the process for termination of the contract due to delay and other acts & omissions of the petitioner. They, however, claim that the invoices/bills raised by the petitioner have been sent to the concerned divisions for verification and, therefore, the decision with regard to payment, if any, to be made to the petitioner would be taken accordingly. CONCLUSION:

¶9Having heard learned counsel for the parties and perused the pleadings, it clearly comes to fore that the dispute between the petitioner and the respondent has arisen out of the contract agreement executed between the parties. The contract agreement contains an Arbitration Clause i.e. Clause 15, in which the parties have agreed upon a procedure to appoint the Arbitrators. Since the respondent has not responded to the notice issued by the petitioner for appointment of an Arbitrator in terms of Clause 15, as such, the petitioner has approached this Court in terms of Section 11(6) of the Act for appointment of the independent Arbitrator.

Page 5

¶10In view of the aforesaid undisputed position, this petition is allowed and Justice Tashi Rabstan, former Chief Justice of this Court, is appointed as a sole Arbitrator to arbitrate the disputes in accordance with law. He shall enter upon reference immediately upon receipt of this order and proceed in the matter to pass the award within a stipulated period.

¶11The Registry shall convey a copy of this order to the learned Arbitrator appointed herein to arbitrate the disputes that have arisen between the parties.

¶12Disposed of.

(SANJEEV KUMAR)

JUDGE

SRINAGAR:

05.12.2025 "ARIF

(i) Whether the order is reportable? Yes/No.

(ii) Whether the order is speaking? Yes/No.

Case details

Parties and counsel

Page 1 Serial No. 04 SUPP LIST IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT SRINAGAR Arb P No. 48/2024 Date of Pronouncement: 05.12.2025 Uploaded on: 08.12.2025 SHAH TECHNICAL CONSULTANTS PRIVATE LIMITED, 407, RAHEJA CENTRE, PLOT No. 214, NARIMAN POINT, MUMBAI-400 021 THROUGH ITS AUTHORIZED REPRESENTATIVE SH. AVISHAKE SINGH JAMWAL, PROJECT COORDINATOR, SHAH TECHNICAL CONSULTANTS PRIVATE LIMTED, PROJECT OFFICE AT PLOT No. 206, 1ST FLOOR, SECTOR-2, CHANNI HIMMAT, JAMMU …PETITIONER(S) Through: Mr. Parvesh Singh Salaria, Advocate (Through V.C) Vs. UT OF J&K THROUGH CHIEF ENGINEER JAL SHAKTI (PHE) DEPARTMENT NEW ENGINEERING COMPLEX, SILK ROAD, RAJ BAGH, SRINAGAR, KASHMIR ...RESPONDENT(S) Through: Mr. Jahangir Ahmad Dar, GA CORAM: HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE

Source: High Court of Jammu and Kashmir and Ladakh, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.