Judgment
JUDGMENT & ORDER (CAV)
Date : 23.06.2023 Heard Mr. K.N. Choudhury, learned Senior Counsel appearing for the petitioner. Also heard Mr. Akhrieu Chusi assisted by Mr. Ravinder, learned counsel for the respondent. PETITIONER'S GRIEVANCE:
¶2The petitioner/STROYPROEKT-OIA JV is a Joint Venture Company (EPC Contractor) having its registered office at Mumbai. The respondent/National Highway & Infrastructure Development Corporation Ltd. (for short 'NHIDCL') is a Public Corporation under the aegis of the Ministry of Road Transport and Highways, Government of India.
¶3The grievance of the petitioner, in brief, is that on 29.05.2020, the petitioner entered into an Engineering Procurement and Construction (for short 'EPC') Agreement for 'Construction of two lanes with hard shoulder of Kohima-Jessami Road' on NH-29 (Old NH-150) from existing km 98.380 (near Chizami Village) to existing km LZA367 (Nagaland Manipur Border) [Design Km 95.700 to design Rm LL7.2AA] [Design Length 21.500 k.m.] in the state of Nagaland under Bharatmala Pariyojna on EPC Mode (Package V) (hereinafter called as 'the Project') vide Annexure P-3 Contract Agreement, dated 29.05.2020. The Contract period commenced on
01.07.2020 and the Contract was initially to be completed within a period of 18 months from the appointed date. The Right of Way (ROW) was handed over to the petitioner on 24.12.2020 by the respondent. On
16.08.2021, for various hurdles faced by the petitioner Company as stated Page No.# 3/16 in the letter including disruption caused due to Covid-19 pandemic, the petitioner sent a letter to the respondent seeking Extension of Time (EOT-I) vide letter No.JV/NHIDCL/PIDCPL/KJ-5/2021-22/28 and letter No.JV/ NHIDCL/KJ-5/2021-22/29. In response to the aforesaid request for EOT sought for by the petitioner, the Authority's Engineer after due assessment of the grounds for request for EOT, on 27.08.2021, recommended EOT for extended period of 6 months based on the force majeure clause of the Contract Agreement due to Covid-19 pandemic as per the instructions of the Department of Expenditure, in accordance with the terms of the Contract. Again, on 02.06.2022, the petitioner, vide its letter No. JV/NHIDCL/PIDCPL/KJ-5/2022-23/HO/14 requested the respondent for another EOT for various reasons like the outbreak of Covid-19 pandemic, infection of 25% of the workforce with Covid-19 virus, quarantine and hospitalization of members of the workforce and mass resignation at the Project Site etc. On 06.06.2022, the Authority's Engineer in view of the aforesaid letter, dated 02.06.2022 by the petitioner seeking another EOT, recommended a total of 385 days of extension till 30.06.2023. Contemporaneously, the petitioner had also applied for recovering the loss caused due to force majeure events from its insurer vide letter No. JV/NHIDCL/KJ-5/2021-22/CAR-1/0S, dated 05.07.2022, issued by the petitioner to their insurer, namely New India Assurance Co. Ltd. However, the respondent vide its letter No.HIDCL /Corres/KJ-V/Vol-1/2020-21, dated
06.07.2022, despite the recommendation of the Authority's Engineer to extend the time, unilaterally declared the petitioner as a Non-Performer. On 09.07.2022, even after declaring the petitioner as a Non Performer, the Project Manager of the respondent, namely Mr. A.K. Singh, General Page No.# 4/16 Manager (P) vide his letter No.NHIDCL/PMU-PFU/KJ-V/LLC-OIA/VOL-111/109 addressed to the Executive Director of the respondent recommended granting extension of time till 29.03.2023. On 14.07.2022, the Authority's Engineer recommended EOT-II with project completion date as 06.06.2023 vide letter No.PIDCPL-SO/420031/GL/1361. Despite the recommendation of the Authority's Engineer to extend the completion date till 06.06.2023, the respondent authority approved EOT-II of the project completion date extended up to 17.12.2022.
¶4The petitioner has stated that thereafter, on 26.09.2022 despite the fact that the Project Manager had previously recommended extension till
29.03.2023, the respondent issued Cure Notice under Clause 23.1 (i) of the Contract for a period of 60 days. On 05.12.2022, the petitioner vide its letter No. JV / NHIDCL / PIDCPL / KJ-5 / 2022-23/ HO /55 submitted the request for EOT-III to the respondent. On 14.12.2022, the Authority's Engineer vide letter No.PIDCPL-PO/420031/CL/1488 recommended EOT-III with Project completion date extended up to 04.07.2023. However, it is contended that the respondent without even considering the petitioner's request for EOT-III vide letter, dated 05.12.2022 and the Authority's Engineer's response vide letter, dated 14.12.2022 published the RFP. On
01.03.2023, the representatives of the respondent, the Authority's Engineer and the petitioner agreed upon another extension of time for a period of 1 month to achieve a DBM length of 5 k.m. in the month of March. However, on 15.03.2023, despite the fact that extension had been granted for a period of one month till the end of March by the respondent vide letter, dated 03.03.2023, Termination Order, dated 15.03.2023 NHIDCL/Nagaland/ Civil Work/KJ/PKG-5/2020/1589 was issued by the Page No.# 5/16 respondent. The respondent issued another letter No. NHIDCL/ PMU-PFU/ KJ-V /SLLC-OIANOL-V/ 180, dated 25.03.2023 stating that the petitioner was carrying out work without the approval of the Authority's Engineer. Aggrieved by the Termination Order, dated 15.03.2023, the petitioner preferred a representation to the respondent on 29.03.2023, which was rejected by the respondent by a non-speaking order vide letter No.NHIDCL/Nagaland/Civil Work/KJ/ PKG-5/2020-21/1617, dated
31.03.2023. Hence, the instant petition. ARGUMENTS:
¶5Mr. K.N. Choudhury, learned Sr. Counsel appearing for the petitioner, submitted that on the question of maintainability of the instant writ petition on account of the arbitration clause included in the Contract Agreement, existence of an alternative remedy is not an absolute bar to the invocation of the writ jurisdiction of the High Court. Mr. Choudhury further submitted that on bare reading of the Contract Agreement, it becomes amply clear that as execution of the Contract work was spread over a long tenure, the intention of the parties to provide for extension reinforces the fact that timely performance was necessary and as such, in the instant case, time is not the essence of the Contract. Mr. Choudhury further submitted that it is an admitted fact that due to hurdles beyond the control of the petitioner, which were explained from time to time, the execution of the Project could not be completed as per programme work submitted by the petitioner even within the extended periods of time, but before completion of the tenure of the third extension, the respondent authority without paying any heed to the recommendation of the Authority's Engineer terminated the Contract abruptly. It has been further Page No.# 6/16 submitted that the respondent issued a 60 day Cure Notice under Clause
23.1 by overlooking the fact that the Authority's Engineer previously proposed an extension upto 06.06.2023. However, Mr. Choudhury submitted that the respondent published the impugned RFP disregarding the recommendation for extension upto 04.07.2023 made in the letter, dated 14.12.2022 causing irreparable pecuniary loss to the petitioner and thereby violated the fundamental rights under Article 14 and Article 19(1)
(g) of the Constitution of India. According to Mr. Choudhury, learned Sr. Counsel, the respondent authority failed to appreciate that as an instrumentality of the State, they had a duty to act fairly and in a non-arbitrary manner. In support of his submission, Mr. Choudhury has relied on the ratio of the decisions rendered by the Hon'ble Supreme Court in-
(1) Welspun Specialty Solutions Ltd. -Vs-Oil and Natural Gas Corporation Ltd., reported in (2022) 2 SCC 382; (2) Union of India and Ors. -Vs-Tantia Construction Pvt. Ltd., reported in (2011) 5 SCC 697 and (3) Jai Bholenath Construction -Vs-The Chief Executive Officer, Zilla Parishad, Nanded & Ors., reported in 2022 LiveLaw (SC) 542.
¶6Mr. Akhrieu Chusi, learned counsel for the respondent, submitted that as per the Project Agreement, initially the Project was to be completed within a period of 18 months from the appointed date, that is,
01.07.2020. Mr. Chusi further submitted that accordingly, the Project had to be completed by 31.12.2021, but the petitioner could only execute the Project by 41.43% till termination of the Contract on 15.03.2023 after due process as per the Contract Agreement. Mr. Chusi submitted that the petitioner was granted sufficient opportunity to improve their deficiencies in execution of the Project and accelerate its progress of work as would be Page No.# 7/16 evident from multiple Show Cause Notices issued and being not satisfied with the Show Cause Reply of the petitioner, on 16.01.2023, the Notice of Intent to Terminate the Contract was issued by the respondent. It has been submitted that despite the aforesaid facts, the petitioner failed to accelerate the execution of the Project and in the backdrop of the compelling circumstances, the respondent had to terminate the Contract by a letter, dated 15.03.2023. Mr. Chusi submitted that the Milestones in Schedule-J of Contract Agreement and Clause-10.3(ii) stipulated Milestone in addition to programme of work at Clause-10.1 for the progress of work to be achieved by the petitioner Contractor. In Schedule-J of the Contract Agreement, the Milestone-I (192nd day) for 10% financial progress, Milestone-II (329th day) for 35% financial progress, Milestone-III (467th day) for 70% financial progress and Project Completion was (549th day) for 100% financial progress. Accordingly, Mr. Chusi submitted, the petitioner has programmed the 3 Milestones work to be completed as the Milestone-I 10%, that is, up to 08.01.2021 and Milestone-II 35%, that is, up to 25.05.2021 and Milestone-III, that is, up to 10.10.2021 and completion date was up to 31.12.2021.
¶7It has been further submitted by Mr. Chusi that the petitioner Contractor has failed to achieve the targeted progress of work execution as stipulated in the programme work submitted by him, but, the petitioner was given the Extension of Time-I and revised the Milestones to the petitioner as there was no progress of work in terms of the stipulated Milestones. Mr. Chusi submitted that the petitioner was given opportunity based on land handover date on 09.12.2020. Thus, the petitioner Page No.# 8/16 Contractor was given Extension of Time (EOT) thrice to complete the Project work after fairly considering the grounds shown for the delay. Accordingly, Mr. Chusi submitted that during the review meeting on progress of execution of the Project, held on 01.03.2023, the petitioner was instructed to target 5 k.m. DBM in the month of March, 2023 keeping in view the onset of monsoon and to achieve the progress of work relatively quicker to cope up with the programme of work. However, till
15.03.2023, the petitioner failed to do any DBM work and as such, due to unsatisfactory and slow progress of work execution, the Contract had to be terminated after due process as per Agreement. Mr. Chusi submitted that due to non-exhaustive fundamental violation of the terms of the Contract repeatedly and in view of the continuing gross default by the petitioner Contractor in fulfilling the contractual obligations thereby causing material adverse impact on the Project, the Contract Agreement with the petitioner by the respondent was terminated vide Termination Notice, dated 15.03.2023, which contains the details of defaults. Mr. Chusi submitted that the Contract Agreement signed between the parties provides for arbitration clause in the event of any dispute, difference or controversy arising out of the execution of the work and as such, the petitioner ought to have resorted to the Arbitration clause for resolution of the disputes in question. In support of his submission, Mr. Chusi has relied on the judgment and order rendered by the Hon'ble Apex Court in Uttar Pradesh Power Transmission Corporation Ltd. and Anr. Vs. CG Power and Industrial Solutions Ltd. and Anr., reported in (2021) 6 SCC 15. APPRECIATION:
¶8In Para 33 of Tantia Construction Pvt. Ltd. (supra), the Hon'ble Page No.# 9/16 Apex Court held that on the question of maintainability of the writ petition on account of the arbitration clause included in the agreement between the parties, it is now well established that an alternative remedy is not an absolute bar to the invocation of the writ jurisdiction of the High Court and that without exhausting such alternative remedy, a writ petition would not be maintainable. It has been further held in Para 34 that notwithstanding the provisions relating to the arbitration clause contained in the agreement, the High Court is fully within its competence to entertain and dispose of the writ petition. In the case in hand, Article 26 of the Contract Agreement vide Annexure P-3 although provides for dispute resolution between the parties, in view of the reliefs seeking for enforcement of fundamental rights of the petitioner as a result of purported failure to observe the principles of natural justice while terminating the Contract in question, the instant writ petition is sustainable in law.
¶9Further, as held in Welspun Speciality Solutions Ltd. (supra), the said Contract Agreement having provided for extension of time for performing the Contract work, time is not the essence of the said Contract.
¶10It is the admitted position that the Contract for the Project in question was awarded on 24.04.2020 and subsequently, the Contract Agreement was signed on 29.05.2020 during the period of Covid-19 pandemic resulting in nationwide lockdown, with a stipulated time period of 18 months for completion of execution of the Project. However, after a delay of 167 days, that is, on 24.12.2020, the ROW was handed over to the petitioner although the Contract period commenced on 01.07.2020, Page No.# 10/16 that is, the appointed date. The Contract was initially agreed to be completed within a period of 18 months from the appointed date. However, the ROW was handed over belatedly on 24.12.2020 by the respondent due to Covid-19 pandemic. On 16.08.2021, the petitioner had submitted an application to the respondent for Extension of Time (EOT-I) vide Annexure P-4 for a further period of 6 months till 30.06.2022 from its original proposed completion date of 31.12.2021. Accordingly, in response thereto, the competent authority of the respondent had accorded approval of EOT of Project Milestone-II and III as per Article 21.6.1(a) of the Contract Agreement till 10.06.2022 vide Annexure P-5 although the Authority's Engineer recommended for 6 months extension on the ground of force majeure clause of the Contract Agreement due to Covid-19 pandemic as per instruction of the Department of Expenditure, in accordance with the Contract vide letter, dated 27.08.2021.
¶11In the context of the aforesaid letter, the competent authority had accorded approval of EOT vide Annexure P-5 as under-Sl. No. Milestone Financial Progress Date as per CA Revised Date as per EOT Milestone-I 10%
08.01.2021 18/06/21 Milestone-II 35%
25.05.2021
02.11.2021 Milestone-III 70%
10.10.2021
20.03.2022 Project Completion Date 100%
31.12.2021
10.06.2022
¶12However, again, the petitioner could not complete the work within the scheduled time due to continuation of Covid-19 pandemic which entailed quarantine and hospitalization of the workforce en masse and mass resignation of workforce at the Project site located at a remote area of the state. Therefore, in the compelling situation, the petitioner Page No.# 11/16 requested for further Extension of Time (EOT-II) by a letter, dated
02.06.2022 vide Annexure P-6 showing the reasons for the unintentional delays in achieving the target work as under-S.N. Reasons Cumulative Delays Delay in handling over of ROW and subsequent hindrance in the ROW from 01.07.2020 to 30.05.2022 and delay is still continuing
699 days Delay due to lockdowns and restrictions due to Covid-19 from
25.03.2020 to 24.09.2020 (184 days) and 14.05.2021 to
30.06.2021 (48 days)
232 days Delay due to unprecedented and unseasonal rains from January 2021 to April 2021 and from September 2021 to December 2022
120 days Total Cumulative delays 1051 days Deduct overlapping delays 352 days Net Delays 699 days
¶13It was stated in the aforesaid letter that the delay occurred within the scheduled completion period of the Contract was 549 days and delay occurred beyond the scheduled completion date was 150 days, total 699 days as shown above. The petitioner attributed the aforesaid hurdles to force majeure in Article 21 of the Contract Agreement. Accordingly, upon consideration of the aforesaid grounds, the petitioner mentioned in the letter, dated 02.06.2022, the Authority's Engineer vide Annexure P-7, letter, dated 06.06.2022, recommended for Extension of Time upto
16.09.2022 for Milestone-II and for Milestone-III upto 31.03.2023 and further, for Milestone-IV upto 30.06.2023. Accordingly, request was approved with the revised EOT by the respondent. It further appears that by a letter, dated 05.12.2022, the petitioner again submitted request for EOT-III vide Annexure P-14. The Authority's Engineer by a letter, dated Page No.# 12/16
14.12.2022 vide Annexure P-15 recommended EOT-III with Project completion date extended upto 04.07.2023. However, the aforesaid recommendations with justifications were not appropriately considered by the respondent and the respondent authority on 27.02.2023 published the RFP for balance work of construction without even considering the petitioner's request for EOT-III vide letter, dated 05.12.2022 and the Authority's Engineer's recommendations vide letter, dated 14.12.2022 aforementioned. Thereafter, on 01.03.2023, the representatives of the respondent, the Authority's Engineer and the petitioner agreed upon for another extension for a period of 1 month to achieve a DBM length of 5 k.m. in the month of March, 2023. It is also seen that the Authority's Engineer by a letter, dated 02.03.2023 vide Annexure P-16 addressed to the petitioner, stated with reference to the VC meeting, dated 01.03.2023, that during discussion with the authorized persons of HQ, NHIDCL, the Contractor agreed to achieve DBM in a length of 5 k.m. in the month of March, 2023 and accordingly, the petitioner was requested to plan and achieve the committed target. On 03.03.2023, the respondent authority wrote a letter to the petitioner vide Annexure P-17 with reference to the first MD review meeting, held on 01.02.2023, the petitioner was instructed to complete 5 k.m. of DBM by the end of March, 2023.
¶14It is further noticed, however, on 15.03.2023, despite the fact that extension had been granted for a period of 1 month, that is, till the end of March, 2023, Termination Order vide Annexure P-1 was issued to the petitioner citing, inter-alia, various contractual defaults, breaches and willful non-performance as well as noncompliance of various notices and instructions of the authority/Authority's Engineer in writing and failure to Page No.# 13/16 achieve the progress in accordance with Clause 23.1(ii) of the Contract Agreement for violation of Article 23 Clause 23.1(i)(c), (d), (f), (g), (i), (p) and (q). Again, on 25.03.2023, the respondent authority issued a letter vide Annexure P-18 alleging that the petitioner continued the execution of the terminated Contract work without the approval of the Authority's Engineer and further, that the respondent was entitled to the ownership of all materials, plant or works and the Project Highway as per Clause 23.7.
(a) of the Contract Agreement clause.
¶15Aggrieved by the aforesaid Contract Termination Order, dated
15.03.2023, the petitioner preferred a representation to the respondent on 29.03.2023 vide Annexure P-19, but by a letter, dated 31.03.2023 vide Annexure P-20 rejected the same on the ground that no valid grounds were found to withhold the aforesaid Termination Order with the approval of the competent authority.
¶16On scrutiny of the various documents annexed to the petition, it is noticed that before terminating the Contract Work, the respondent authority had reviewed the progress of work of the petitioner and held the opinion that the petitioner had failed to take corrective/curative steps for expediting the progress of work despite all possible support was given by the respondent and accordingly, notice was also issued to the petitioner vide letter, dated 30.03.2022 in the form of a Show Cause Notice for declaring as Non Performer due to slow progress and poor planning of work. Accordingly, the petitioner in reply, dated 21.04.2022 admitted the defaults on their part admitting as quoted hereinbelow-Page No.# 14/16 "We admitted that the Milestone-II and Milestone-III were failed due to poor planning and poor management, and overall work progress is not satisfactory. We assured that all necessary efforts are being made and actions taken to streamline and expedite the work progress. We also assured to start the pending works immediately and complete the project by March, 2023."
¶17The aforesaid reply was examined by the respondent authority and on being not satisfied with the overall performance, declared the petitioner as Non Performer and accordingly, the petitioner Contractor was debarred from participating in any bid with MoRTH or its executing agencies till such time the Contractor is removed from the list of Non Performer vide Annexure P-9, Office order, dated 06.07.2022. Thus, it appears that by virtue of being a Non Performer the petitioner was marked responsible for failure to live up to the contractual obligations heralding the inevitable consequence of termination of the Contract in due course.
¶18According to the respondent authority, the programme of work and dismal progress by the petitioner was as follows-Month Mar-Apr-May-Jun-Jul-Aug-Sep-Oct-Nov-Dec-Jan-Feb-23 Mar-23 % of work programme submitted by the Contractor
13.59
12.12
10.13
6.44
2.34
8.01
13.23
16.44
17.82
9.89
24.75
26.36
11.12 % of Progress achieved by the Contractor
1.54
0.83
0.91
2.98
0.16
0.37
0.37
0.76
0.8
2.32
0.91
0.73
0.38 Page No.# 15/16
¶19It may be noted here that Article 23.1(i) provides the detailed procedure for Termination of Contract for contractor's default, inter alia, providing that when the Contractor does not achieve the latest outstanding Project Milestone due in accordance with the provisions of Schedule-J, subject to any time extension, and continues to be in default for 45(forty five) days. So far the termination of Contract is concerned, Article 23.1(ii) provides that upon occurrence of a Contractor Default, the authority shall be entitled to terminate the Agreement by issuing a Termination Notice to the Contractor; provided that before issuing the Termination Notice, the authority shall by a notice inform the Contractor of its intention to issue such Termination Notice and grant 15(fifteen) days to the Contractor to make a representation and may after the expiry of such 15 days, whether or not it is in receipt of such representation issue the Termination Notice.
¶20Although the respondent authority published the RFP for the balance works without passing a speaking order of acceptance or rejection of the petitioner's request for EOT-III, vide letter, dated 05.12.2022 and the Authority's Engineer's response vide letter, dated 14.12.2022, while the EOT for performing the Contract Work was in subsistence, it cannot be said that the same was passed arbitrarily and illegally because from time to time, the hurdles faced by the petitioner in executing the work as per their assured schedules were duly considered by the respondent authority and granted accordingly. In this context, the admission of default of the petitioner Contractor quoted above may pertinently be referred.
¶21It is, therefore, apparent on record that the decision making process Page No.# 16/16 in terminating the Contract work was based on proper assessment of work progress and appreciation of the circumstances that had an impact on the delay in completion of the work, which involves public interest at large. In other words, the award of the Contract to the petitioner for construction of public road (National Highway) in a State like Nagaland was in public interest and the termination of the said Contract awarded to the petitioner was also in public interest where no interference of this Court in exercise of the extraordinary jurisdiction under Article 226 of the Constitution of India by way of review is warranted. CONCLUSION:
¶22Accordingly, the writ petition stands dismissed.
¶23The interim order, dated 03.04.2023 stands vacated.
The writ petition stands disposed of accordingly.
JUDGE Comparing Assistant
Case details
Parties and counsel
Page No.# 1/16 GAHC020001172023 THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH) Case No. : WP(C)/44/2023 STROYPROEKT-OIA JV THROUGH ITS AUTHORISED REPRESENTATIVE, ANOOP GUPTA, OIA HOUSE, 470 CARDINAL GRACIOUS ROAD, ANDHERI (E), MUMBAI- 400099 VERSUS NATIONAL HIGH WAY AND INFRASTRUCTURE DEVELOPMENT CORPORATION MINISTRY OF ROAD AND HIGHWAYS, GOVT. OF INDIA, 3RD FLOOR, PTI BUILDING, 4-PARLIAMENT STREET, NEW DELHI 110001 Advocate for the Petitioner : KN CHOUDHURY Advocate for the Respondent : BEFORE HON'BLE MR. JUSTICE AJIT BORTHAKUR For the petitioner : Mr. K.N. Choudhury, Sr. Advocate For the respondent : Mr. Akhrieu Chusi, Advocate Mr. Ravinder, Advocate Date of hearing : 19.06.2023 Date of Judgment/ Order : 23.06.2023 Page No.# 2/16
Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.