VoxJuris
Home › High Courts › Delhi High Court 2011 › High Court of Delhi

New Okhla Industrial Development Authority v. Km Paramjit & Anr

Court
High Court of Delhi
Decided
1 November 2011
Bench
Indermeet Kaurauthor
Case no.
CM(M) 1278/2011

Follow Delhi High CourtFollow Indermeet Kaur

Judgment

INDERMEET KAUR, J. (Oral)

¶1The order impugned before this court is the order dated

11.03.2011 vide which the application filed by the appellant under Section 5 of the Limitation Act seeking condonation of delay of 78 days in filing the appeal had been dismissed.

¶2Record shows that a suit for permanent injunction and

declaration had been filed by the plaintiff against the two defendants; the prayer in the suit was that the defendants i.e the New Okhla Industrial Development Authority as also the DDA be restrained from abolishing the suit property and interfering in the peaceful possession of the property. On the pleadings of the parties issues were framed as the main bone of contention was as to whether the property falls in Noida or in Delhi. The Trial Court vide judgment dated 01.05.2010 had decreed the suit in favour of the plaintiff holding that the suit property falls within Illaqa Shahdara, Delhi. Appeal against the aforenoted judgment was filed by the petitioner i.e. the New Okhla Industrial Development Authority after a delay of 78 days. In the application under Section 5 of the Limitation Act the delay has been explained in para Nos. 2 and 3.

¶3It is not in dispute and as it is borne out from the record that the certified copy of the judgment and decree dated

01.05.2010 had been applied for on 07.05.2010 which was obtained on 17.05.2010; appeal was to be filed till 17.06.2010; it was filed belatedly for the reason that the earlier counsel who was dealing with the matter had been changed; new counsel had requested the earlier counsel for handing over the complete case file which was given to the new counsel only on 26.06.2010; the

inspection report dated 07.01.2005 was found missing which was to be obtained before the appeal could be filed; certified copy of these papers were made available only on 28.07.2010; this was the explanation furnished by the petitioner for the delay in filing the appeal.

¶4The words 'sufficient cause' as appearing in Section 5 of the Limitation Act have to be construed liberally so as to advance substantial justice to the parties; a litigant should not be shut out at the threshold and be deprived of the opportunity to be heard on merits; delay may be condoned provided that the applicant is able to furnish a sufficiently justifiable explanation for his delay. No hard and fast rule can be laid down. Each case has to be decided on its factual matrix. Unless there is lack of bona fides or a total inaction or negligence on the part of the litigant, the protection of Section 5 should not be deprived to a party; mistake of a counsel may also amount to a sufficient cause for condonation of delay; it is always a question of fact.

¶5In the instant case, keeping in view the explanation furnished by the learned counsel for the petitioner in the application which was duly supported by the affidavit of the Tehsildar of the petitioner who had stated that this application had been drafted on the basis of the relevant record, the

justification furnished by the petitioner for not filing the appeal within time has been explained. The petitioner should not be declined a hearing on merits for the fault which at best is attributable to his counsel. The impugned order is accordingly set aside. Delay in filing the appeal is condoned. This order is passed subject to payment of Rs. 5,000/- as costs. The parties to appear before the First Appellate Court on

15.11.2011 and the Trial Court shall proceed to dispose of the appeal on its merits.

INDERMEET KAUR, J

NOVEMBER 01, 2011 rb

Case details

Parties and counsel

* IN THE HIGH COURT OF DELHI AT NEW DELHI % Date of Judgment: 01.11.2011 + CM(M) 1278/2011 NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY ..... Petitioner Through: Mr. H.L. Raina, Advocate. versus KM PARAMJIT & ANR ..... Respondents Through: Mr. I.V. Raghav and Mr. S.B. Raghav, Advocates for R-1. + CM(M) 1279/2011 NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY ..... Petitioner Through: Mr. H.L. Raina, Advocate. versus VINOD KUMAR MITTAL & ANR ..... Respondents Through: Mr. I.V. Raghav and Mr. S.B. Raghav, Advocates for R-1. + CM(M) 1280/2011 NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY ..... Petitioner Through: Mr. H.L. Raina, Advocate. versus RAJESHWAR PRASAD & ANR ..... Respondents Through: Mr. I.V. Raghav and Mr. S.B. Raghav, Advocates for R-1. + CM(M) 1281/2011 NEW OKHLA INDUSTRIAL DEVELOPMENT AUTHORITY ..... Petitioner Through: Mr. H.L. Raina, Advocate. versus NEW ASHOK NAGAR BLOCK E & ED DEV ASSOCIATION & ORS ..... Respondents Through: Mr. Robin George , Mr. Satish Kumar Bhatia and Mr. Hukum Singh, Advocates for R-1, 3, 4, 6 to 15, 19 & 20. Mr. I.V. Raghav and Mr. S.B. Raghav, Advocates for R-16, 17, 18 & 21. CORAM: HON'BLE MS. JUSTICE INDERMEET KAUR 1. Whether the Reporters of local papers may be allowed to see the judgment? 2. To be referred to the Reporter or not? 3. Whether the judgment should be reported in the Digest?

Source: High Court of Delhi, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.