- Court
- High Court of Jammu and Kashmir and Ladakh
- Decided
- 5 October 2026
- Bench
- Shahzad Azeem, Judge
- Case no.
- WP(C) 3185/2026
Judgment
ORDER (ORAL)
05.10.2026
¶1The petitioner has called in question the show cause notice dated
07.08.2026 issued by respondent No. 4 (Executive Engineer, PMGSY Division Mahore, District Reasi) and further seeks a direction to the respondents to abide by the terms and conditions of the contract and to hand over the work site to the petitioner as per the contract. Sr. No. 144
WP(C) No. 3185/2026
¶2The precise grievance of the petitioner is that he has been allotted the work of construction and maintenance of road from L043 Pansa to Prankote/Parankot, Package No. JK14-635, Regular PMGSY (Batch-I, 2018-19), Stage-II, Block Arnas, District Reasi, length 20.600 Kms. The petitioner claims that the length of the said road is 20.600 kms, which was to be completed within the stipulated time as per the agreement entered between the petitioner and the respondent-department.
¶3The precise submission of the petitioner is that despite having observed all the codal formalities and having executed the work as per the contract, he came across the impugned show cause notice whereby, besides to cancel of the contract, he has also been asked to show cause as to why his license be not cancelled.
¶4With the above factual narration, learned counsel for the petitioner submits that though he has duly replied to the show cause notice, but till date the respondents have not considered the same and are contemplating to proceed against the petitioner. It is further submitted by learned counsel for the petitioner that he would be satisfied in case the respondents are directed to consider the representation/reply filed by the petitioner, before taking the proposed action.
¶5In view of the submissions made, instant petition is disposed of with a direction to the respondents to consider the representation/reply filed by the petitioner to the show cause notice and thereafter proceed into the matter strictly in accordance with the terms and conditions of the contract entered
WP(C) No. 3185/2026
between the parties and the law governing the subject. Let this exercise be completed within a period of two weeks from the date a copy of this order is made available to the respondents. Till then, respondents shall not give effect to the impugned show cause notice dated 07.08.2026.
¶6Disposed of, accordingly.
(Shahzad Azeem) Judge Jammu
05.10.2026 Mihul
Whether the order is reportable?
Whether the order is speaking?
Case details
Parties and counsel
HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU WP (C) No. 3185/2026 M/s A.N. Builders Through its proprietor Faisal Syeed, Age 48 years S/o Mohamd Syed R/o Lane No. 1, Gulshanabad Fazibal K.P. Road, Anantnag, J&K Date of pronouncement: 05.10.2026 Date of uploading: 05.10.2026 …..Petitioner(s) Through: Mr. M. Nadeem Bhat, Advocate Vs 1. UT of J&K through Commissioner/Secretary to Government Public Works Department, Civil Secretariat, Jammu. 2. Chief Engineer, PMGSY/JKRRDA, Jammu. 3. Superintending Engineer, PMGSY Circle Reasi-Udhampur, Reasi. 4. Executive Engineer, PMGSY Division Mahore, District Reasi. 5. Assistant Executive Engineer, PMGSY Sub- Division Arnas, District Reasi. .…. Respondent(s) Through: Coram: HON'BLE MR. JUSTICE SHAHZAD AZEEM, JUDGE
Source: High Court of Jammu and Kashmir and Ladakh, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.