Amiya Kumar Pathak v. The State of Assam and 3 Ors

Disposed Of
Court
High Court of Gauhati
Decided
16 October 2023
Bench
Manish Choudhuryauthor
Case no.
WP(C) 4325/2023

Follow Gauhati High CourtFollow Manish Choudhury

Judgment

ORDER Date : 16-10-2023 Hears Ms. S.A. Khalifa, learned counsel for the petitioner and Ms. M.D. Bora, learned Standing Counsel, Transport Department for all the respondents.

¶2The petitioner has preferred the instant writ petition projecting inter alia that in response to the Notice Inviting Tender [NIT] dated 19.01.2021 for "Minor repairing, electrification, painting works of T.F. Sukrewwar of G.N ferry service" ['the Contract-Work no. 1', for short], he submitted his tender on 01.02.2021 and the respondent authorities through the Executive Engineer, I.W.T. Division, Guwahati issued a Letter of Acceptance [LoA] vide Letter bearing no. EWT/[T]298/07-08/1550 dated 02.02.2021 [Annexure-A]. It is the case of the petitioner that the petitioner had carried out the contract-work as per specifications provided with the rates as enclosure to the Letter of Acceptance [LoA] dated 02.02.2021. On

23.02.2022, the Executive Engineer, I.W.T. Division, Guwahati had issued another work order vide Letter bearing no. EWT/[T]550/VVIP/2019-20/2356 dated 23.02.2022 [Annexure-B] for "Painting works of vessel TF Karnachal of G/N ferry service in connection with VVIP programme" ['the Contract-Work no. 2', for short]. As per the specification provided with the rates as enclosure thereto similarly, the petitioner was issued 2 [two] other work orders vide Letter bearing no. EWT/[T]550/VVIP/2019-20/2344 dated 23.02.2022 [Annexure-C] for "Painting works of vessel MV Narayan of G/N ferry service in connection with VVIP programme" ['the Contract-Work no. 3', for short] and Letter bearing no. EWT/ [T]550/VVIP/2019-2020/2350 dated 23.02.2022 [Annexure-D] for "Painting works of vessel RPL Baghbor of G/N ferry service in connection with VVIP programme" ['the Contract-Work no. 4', for short].

¶3The petitioner has averred that after executing all the 4 [four] Contract-Works awarded to him, he had submitted the final Bills in that respect and when the respondent authorities Page No. 3/5 did not release an amount of ₹ 5,83,439/- against those final Bills, he is constrained to approach this Court by the writ petition seeking inter alia a direction to the respondent authorities to disburse of the said amount of ₹ 5,83,439/-.

¶4The respondent no. 2 i.e. the Director of Inland Water Transport, Assam has submitted a counter affidavit on 28.08.2023 stating inter alia as under :-

¶4That with regard to the statements made in Paragraph no. 7 of the writ petition the deponent begs to state that as per record available in the office of the Executive Engineer, IWT, Ulubari Division, Guwahati the work of [i] Minor repairing, electrification, painting works of T.F. Sukreswar of G/N ferry service, [ii] painting works of vessel TF Kamachal of G/N ferry service in connection with VVIP programmes, [iii] painting works of vessel MV Naranarayan of G/N ferry service in connection with VVIP programmes, and [iv] painting works of vessel RPL Baghbar of G/N ferry service in connection with VVIP programmes was awarded to the petitioner. The petitioner executed all the four works and submitted bills amounting to Rs. 5,83,037/-. As such the outstanding liability due to the writ petitioner for the above mentioned works is Rs. 5,83,037.00 which is admitted.

¶5That with regard to the statements made in Paragraph no. 8 of the writ petition the deponent begs to state that, the writ petitioner executed various works under different head of Account. However due to insufficient fund under the proper Head of Account the liability to the writ petitioner could not be fully cleared. The deponent further begs to submit that at the time of issue of preliminary work order it was clearly mentioned that payment will be made subject to the availability of fund. * * *

¶9That with regard to the statements made in Paragraph no. 12 of the writ petition the deponent begs to state that, as per record the various prior works was awarded to the petitioner and the payment against that works has been duly made by the Department. However due to the paucity of funds the outstanding liability towards the writ petitioner has not been cleared. As and when the higher authority provides the funds, the liability towards the writ petitioner would be cleared. Page No. 4/5

¶11That with regard to the statements made in Paragraph no. 14 of the writ petition the deponent beg to state that, on receipt of the fund under proper head of account, strict chronological order will be maintained for making payment by displaying the name of contractors who is entitled to get the payment by covering the amount of ceiling allotment and contractor will be communicated to receive the payment."

¶5Ms. Bora, learned Standing Counsel, Transport Department has submitted that since the outstanding liability to the extent of ₹ 5,83,037/- has been admitted in the affidavit filed on behalf of the respondent no. 2, who is the Head of the Directorate, this writ petition can be disposed of in the line of the directions contained in the Full Bench judgment of this Court, rendered on 29.09.2008 in Writ Appeal no. 484/2005 [Tamsher Ali & others vs. State of Assam & others], reported in 2008 [4] GLT 1 [FB] and similar other 194 writ petitions.

¶6Ms. Khalifa, learned counsel for the petitioner has agreed to such submissions of Ms. Bora.

¶7From the statements and averments made in the counter affidavit filed by the respondent no. 2 i.e. the Director of Inland Water Transport, Assam as the Head of the Directorate, it is evident that the respondent authorities had admitted the liability to the extent of ₹ 5,83,037/- in respect of the 4 [four] Contract-Works executed by the petitioner on behalf of the respondent authorities. A stand has been taken therein that due to availability of the sufficient fund in the proper Head of Account, the liability of the writ petitioner could not be disbursed till date. In such view of the matter, this Court is of the considered view that the writ petition can be disposed of with a direction in similar lines as directed in the Tamsher Ali [supra]. Accordingly, this writ petition is disposed of with a direction to the respondent authorities to disburse the amount of ₹ 5,83,037/- to the petitioner strictly in terms of the directions made in Tamsher Ali [supra], more particularly, by strictly adhering to the chronological order of claims pending in the Directorate of Inland Water Transport, Assam, on availability of fund.

Page No. 5/5

¶8This order disposes of the writ petition.

JUDGE Comparing Assistant

Case details

Parties and counsel

PageoNo.o1/5 GAHC010163852023 ooooooo ooooooooooooooo ooooooooooooooooTHEoGAUHATIoHIGHoCOURTo (HIGHoCOURToOFoASSAM,oNAGALAND,oMIZORAMoANDoARUNACHALoPRADESH)o CaseoNo.o:oWP(C)/4325/2023o AMIYAoKUMARoPATHAKo S/O-oLATEoKANURAMoPATHAK,o R/O-oHOUSINGoROAD,oHOUSEoNO-4,o P.O-oSILPUKHURI,oGUWAHATI-03,oKAMRUPo(M),oASSAM VERSUSo THEoSTATEoOFoASSAMoANDo3oORSo REP.oBYoTHEoCOMMISSIONERoANDoSECRETARYoTOoTHEoGOVERNMENToOF ASSAM,oINLANDoWATERoTRANSPORToDEPARTMENT,oULUBARI,o GUWAHATI-7 2:THEoDIRECTOR oINLANDoWATERoTRANSPORToDEPARTMENT oULUBARI oGUWAHATI-7 3:THEoDEPUTYoDIRECTOR oINLANDoWATERoTRANSPORToDEPARTMENT oULUBARI oGUWAHATI-7 4:THEoASSISTANToEXECUTIVEoENGINEERo(T/C) oINLANDoWATERoTRANSPORToDEPARTMENT oULUBARI oGUWAHATI-o AdvocateoforotheoPetitionerooooo:oMRS.oKoDEVIo AdvocateoforotheoRespondento:oSC,oIWToo oooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooooo Page No. 2/5 BEFORE HONOURABLE MR. JUSTICE MANISH CHOUDHURY

Source: High Court of Gauhati, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.