VoxJuris

Real Estate (Regulation and Development) Act, 2016 · Chapter VIII: Offences, Penalties and Adjudication

Section 63: Penalty for failure to comply with orders of Authority by promoter

If any promoter, who fails to comply with, or contravenes any of the orders or directions of the Authority, he shall be liable to a penalty for every day during which such default continues, which may cumulatively extend up to five per cent., of the estimated cost of the real estate project as determined by the Authority.

Source: India Code (indiacode.gov.in), the consolidated text published by the Legislative Department, Government of India. Text as updated on India Code on 14 October 2026. Words in square brackets [ ] were inserted or substituted by later amending Acts, and *** marks words omitted by an amendment. The amendment footnotes are not reproduced here. Official text on India Code.

Supreme Court judgments citing the section 63

No Supreme Court judgment in our database cites this section yet.