Judgment
JUDGEMENT
¶1The petitioner is seeking appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996.
¶2There is a valid arbitration agreement between the parties contained in clause No.19 of the agreement dated 5th March, 2004. Disputes have arisen between the parties under the agreement. The petitioner has validly invoked the arbitration vide notice dated 10th December, 2013.
¶3The petition is allowed and Mr. Justice R.C. Jain (Retd.) is appointed as sole arbitrator to adjudicate the disputes between the parties including their claims and counter-claims.
¶4The arbitration shall take place under the aegis of Delhi International Arbitration Centre ('DAC'). The fees of the learned Arbitrator shall be in terms of the Delhi International Arbitration Centre (DAC) (Administrative Cost Arbitrator's Fees) Rules.
¶5Copy of this order be given dasti to counsel for the petitioner under the signature of the Court Master. A copy of this order be delivered to the learned Arbitrator as well as Additional Coordinator, DAC forthwith.
J.R. MIDHA, J. September 18, 2015 ak
Case details
Parties and counsel
* IN THE HIGH COURT OF DELHI AT NEW DELHI % Dated of Decision: 18.09.2015 + ARB.P. 281/2014 M/S PRIMO CONSTRUCTION CO ..... Petitioner Through: Mr. S.K. Upadhyay, Advocate. versus ENERGO ENGINEERING PROJECTS LTD AND ORS ..... Respondents Through: Ms. Vaishali Kakra and Mr. Irfar Ahmed, Advocates. CORAM: HON'BLE MR. JUSTICE J.R. MIDHA
Source: High Court of Delhi, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.