O R D E R %

20.11.2025

¶1This hearing has been done through hybrid mode.

¶2The present petition under Sections 11 and 12 of the Contempt of Courts Act, 1971 seeks the following prayers: -

"a) Inquire into the commission of Civil Contempt of Court as defined u/s 2(b) of contempt Act by the respondents for making false and wrongful submissions before this Hon'ble Court in CRL.M.C. No-738/2021 vide order dated-18.03.2025 and for filing a frivolous and misleading affidavit;

b) Order for punishment of respondents in accordance with section 12 of the Contempt of Courts Act.

c) Pass such other or further orders as this Hon'ble Court may deem just and proper in the facts and circumstances of the case."

¶3Learned counsel appearing on behalf of the petitioner submits that first supplementary agreement has been arrived at between the parties on

27.08.2025. Copy of the same has been handed over in the Court today and This is a digitally signed order. the same has been taken on record. It is further pointed out that as per 'Clause 7' of the said agreement the following has been agreed: -

"7. It is further agreed that the Second party within a period of 10 days from the execution of this agreement, shall also withdraw two petitions Cont. Cas(C) 1041/2025 & 968/2025 filed before the Hon'ble High Court of Delhi at New Delhi. However, the Second Party has a right to revive the proceedings if the mandate of this agreement is not complied by the First Party."

¶4In view of the above, the present petition is dismissed as withdrawn and disposed of with liberty to revive the present petition in case of non-compliance of the conditions mentioned in the aforesaid agreement dated

27.08.2025.

¶5Pending application(s), if any, also stand disposed of.

AMIT SHARMA, J NOVEMBER 20, 2025/kr

This is a digitally signed order.

Case details

Parties and counsel

* IN THE HIGH COURT OF DELHI AT NEW DELHI + CONT.CAS(C) 1041/2025 CHANDAN BHATIA .....Petitioner Through: Mr. Banke Bihari Jee, Mr. Adarsh Singh, Advs. versus TULSIANI CONSTRUCTION PVT LTD & ORS......Respondents Through: Ms. Pratima N. Lakra CGSC with Mr. Shailendra Kumar Mishra, Mr. Priyam Sharma, Mr. Chaanakya Kene, Advs. for R-1. CORAM: HON'BLE MR. JUSTICE AMIT SHARMA

Source: High Court of Delhi, through the eCourts High Court services, via the Indian High Court Judgments open dataset by Dattam Labs (CC BY 4.0). Text was extracted from the official PDF and may contain conversion errors. Check the official PDF before relying on it.